I built a realtime Scottish data centre tracker, mapping every planning application as they come in.
24 sites. 13 councils. About 5,500MW of stated capacity.
The biggest by stated capacity:
• Chapelcross, near Annan: 1GW
• Cato, Auchtertool (Fife): 600MW
• Ravenscraig: 550MW
• Rufus, Hurlford: 540MW
• Drumshangie, near Airdrie: 500MW
Several haven't published a figure at all, so the real total is higher.
Most are at the very start: a notice that an application is coming, or a screening request asking whether a full environmental assessment is needed.
Only a handful have full or outline applications in, including Larbert, Chapelcross, Auchtertool, Spango Valley and Westerhill.
South Gyle (212MW) was refused by councillors and is now with Scottish Ministers on appeal.
Wester Hermiston (200MW) has been told it needs a full environmental impact assessment. There's no application yet.
Tap any site to see the developer, where its capacity figure comes from, and every filing linked to the council's own documents, so you can read the actual applications rather than the press releases.
It checks every Scottish council's planning portal, so a new notice, application or decision shows up on the map as soon as it's lodged. Have a look: